Tooling Costs
Charge for cutting tools with a tool kit cost spread over parts, plus a wear charge per machine hour, without counting your tools twice.
On this page
This tab sets what tool kits and tool wear add to every quote. A tool kit is the full set of cutters or inserts a job family uses up before you replace them. Quote spreads its cost over the parts one kit makes, and can also add a charge for every hour a machine is cutting.
Open it from the Pricing page, fifth tab, Tooling. Both charges are added into one tool line per part, before yield and markup.

Milling Tool Kit Cost#
Unit: per kit, 0 turns it off. Starting value: 44. Where: Pricing, Tooling.
One full milling tool kit, spread over the parts it makes. Off adds nothing to quotes. The toggle suggests 20 when you switch it on.
Change it when: set it to what you really spend on tools for a job family.
Lathe Tool Kit Cost#
Unit: per kit, 0 turns it off. Starting value: 18. Where: Pricing, Tooling.
One full lathe insert kit, used instead of the milling kit on turning and mill-turn routes. Off adds nothing to quotes.
The lathe kit is used for pure turning parts. Otherwise the milling kit is used. If the lathe kit cost is 0 or less, the milling kit is used.
Tool Kit Life (Units)#
Unit: parts. Starting value: 250. Where: Pricing, Tooling. Also shown as Parts Per Tool Kit.
How many parts one kit makes before it is replaced.
Whole kits needed = quantity / kit life, rounded up. Cost per part = kits x kit cost / quantity.
Change it when: set it to how many parts a kit really lasts. Use a smaller number for hard materials that eat tools.
Worked Example: An Order Of Ten#
With kit cost 44 and kit life 250, an order of 10 needs 1 whole kit, so it pays the full kit: 44 / 10 = 4.40 per part.
| Quantity | Kits | Kit cost per part |
|---|---|---|
| 10 | 1 | 4.40 |
| 250 | 1 | 0.18 |
| 251 | 2 | 0.35 |
Kit cost mainly punishes small orders, because a small order pays for a whole kit it barely uses.
Tool Wear Per Machine Hour#
Unit: per hour, 0 turns it off. Starting value: 0. Where: Pricing, Tooling.
Extra tool cost for every hour a machine is cutting. A long cycle wears tools more than a short one. The toggle suggests 2 when you switch it on.
wear = rate x cutting hours, where cutting hours = (total minutes - clamping minutes) / 60
Example: at a rate of 2 per hour, a part with 30 cutting minutes adds 0.50 per part.
Change it when: use wear for hard materials with long cycles, where tool cost follows machine time more than part count.
Watch out: filling both a high kit cost and a high wear rate counts your tools twice. Pick the one that matches how your tools are actually consumed, or keep both low.